Information on the constructing works of Beryozovski mine as of July 1, 2009
1. Sinking works in shaft ¹ 5
As of July 1, 2009 the shaft is sunk up to the level of 222,4 m and is fixed with the concrete.
The works relating to the tubing mounting in the interval from the level of 180.3 m up to the level
of 1.5 m (119 rings are mounted and caulked) are finished.
2. Sinking works in shaft ¹ 6
As of July 1, 2009 the shaft is sunk up to the level of 186.4 m and is fixed with the concrete.
The tubing mounting works are being conducted.
The tubing column is mounted from the level of 180.3 m up to the level of 9.0 m (total -- 171.3 m), 114 rings.
3. Refrigerating station
The refrigerating station operates in order to refrigerate the shaft ¹ 5 and ¹ 6 rocks.
4. The administration and welfare building
The works relating to the building frame mounting have been finished. The works relating to wall
and cross wall masonry, installing the monolith elements of building, running water and
sewage systems, heating and ventilation are going on. The interior finishing works have started.
May 7, 2009
The solemn commissioning of the 1st stage of the Krasnoslobodski mine took place,
the first skip with ore using a constant scheme was hoisted.
|
|
|
| |
|
|
|
|
| |